Project Datasheet

Bridges Market Sector

Project: Rail Bridge. Number 283 for M6 Toll road  
[No Images on File]


For more details please contact:

Peter Miller
Director
Watson Steel Structures Ltd
+44 (0) 1204 696 675
enquiries@watsonsteel.co.uk
Client: Midland Expressway Ltd
Location: Shenstone
Staffordshire
Country: England
Partners: Main Contractor: C.A.M.B.B.A.
Consulting Engineer: Arup - Atkins
Architect: Arup-Atkins
Statistics: Total Tonnage: 485 tonnes
Programme: 
Completion Date:  July 2001
Overview: This 54m long twin track rail bridge weighing 485 tonnes was constructed by Watson Steel for the Birmingham Northern Relief Road. The entire bridge was fully assembled in the Bolton Works to ensure fit up before being dismantled and delivered to site. The bridge was erected over a 40 hour possession period in November 2001.
       